Taken from the roll call in the town’s own minutes. The minutes record who was not there and almost never why.
What was decided (2 motions)
1 carried, 1 recorded otherwise. Every motion below is printed as the minutes print it.
That Report PW 39-2021, dated August 5, 2021, South Niagara Falls Wastewater Treatment Plant - Budget and Property, BE RECEIVED and the following recommendation BE APPROVED: 1. That a budget increase to the capital projects associated with the new South Niagara Falls Wastewater Treatment Plant BE CONSIDERED as part of the 2022 budget process.
Moved by Councillor Rigby, seconded by Councillor Ugulini
Carried
That CWCD 2021-191, being a memorandum from B. Zvaniga, Interim, Commissioner, Public Works, dated September 3, 2021, respecting Response to Councillor Information Request re Ministry of Environment, Conservation and Parks Investigation, BE
Moved by Councillor Gale, seconded by Councillor Whalen